THE true cost of the millions of ringgit in public funds that are reported as lost in the Auditor-General’s Report 2013 must be tabulated in order to drive home the importance of stemming this endless haemorrhage.
Two prominent cases highlighted in the first of the three-part AG’s Report released last week, illustrate the unconscionable wastage of money that leaves a black mark on the civil service.
The first case involves the RM342.55 million Paya Peda Dam in Terengganu, which the Report said, was marred by the inexperience and lack of expertise of the contractors JAKS Resources Bhd and Pembinaan Sujaman Sdn Bhd.
The troubling question is why the contract was awarded by direct negotiation when an open tender would have easily identified a competent contractor for the job.
The AG found that not only did the contractors lack the experience needed for the construction of a dam with a hydro-mechanical gate system, they had also flouted international guidelines, failed to submit preliminary drawings resulting in an incomplete submission for the project and made wrong calculations on components of the project.
This scandalous litany of flaws warrants an independent investigation into the gaps in accountability that allow such a state of affairs to exist.
The Report notes that the project’s shortcomings resulted in a flood two years ago, and affected the targeted increase in paddy yields in the Besut district.
Moreover, flood damage carries many direct and indirect costs, ranging from destruction of property to loss of income and even lives, and to loss in property value and reduced investor confidence.
The other glaring case involves the Kuantan court complex, the construction of which was delayed by 560 days, resulting in a cost increase of some RM19.56 million, according to the Report.
The reasons given for the delay were poor planning in the design and scope of construction work. Among other things, the terms of the contract were disregarded and there were differences between the As-Built drawings and actual construction, the Report said.
Some 158 weeks after the scheduled completion date and almost RM20 million in extra costs later, the complex was completed.
Considering that the extra millions in wasted funds could have gone towards social services and amenities for the underprivileged sectors of society, it is a grave crime against the less fortunate that the country’s wealth continues to be squandered in this way.
Being scrupulous about the use of public funds is not just a matter of financial accountability, it is a solemn duty for civil servants and society at large to ensure that the money saved reaches the most deserving people in our midst.
So, the wastage that the AG dutifully reports without fail every year is really a tally of the opportunities for a better life that are snatched from the people at the bottom of society.
Read more: http://www.fz.com/content/wasted-millions-must-be-measured-stolen-futures#ixzz2ypzasyFL